Confidential Data Center Buildout

INDUSTRY

Mission Critical

TIMELINE

24 Months

LOCATION

Arizona

IMG 1311 2 scaled
IMG 1331 1

OVERVIEW

This large-scale data center build marked a first for the Phoenix valley, setting a new standard in both size and capacity for the region at the time of launch.

Loenbro was selected to lead electrical execution with a field-proven team of 250+ electricians, managing everything from MV transformer and generator installs to full commissioning. The result: 12MW commissioned every 6 weeks, ahead of schedule, with zero recordable incidents.

By month eight, our teams had delivered the fastest construction pace ever achieved for a facility of this scope while meeting strict safety, quality, and commissioning benchmarks.

This project showcases what Loenbro brings to every mission-critical build: trusted manpower, operational discipline, and the ability to execute under pressure, without compromise.

See the success

  • Data Center Electrical Services

    • 32,000′ of MC Cable Installed

    • 70,000′ of MV Cable Installed

    • 40 MV Transformers Installed

    • 40 Generators Installed

    • 80 PDUs Installed

    • Rolling 12MW data hall turns over every 30 days

    • Record 30-day data hall commissioning cycle L3-IST