SERVICES PROVIDED:
PROJECT DESCRIPTION:
- Three new MCC sections, along with an 4000A ATS, Back -up Generator, Utility Transformer, and a CT Cabinet.
- Over 300 feet each of a 1600A bus duct and a 4000A bus duct.
- Over 10 Miles of Multi-conductor cable ranging from 3/C#12 to #1000Kcmil along with Megger Testing, Hipot testing, and terminations as required.
- Installation of miscellaneous 480V Power Panels, Lighting Panels, step down transformers along with a combined 538 Light fixtures, convenience outlets and welding receptacles.
- Cable tray installation to provide raceways interconnecting the three buildings and internal raceways for conduit drops to multiple Power, Control and Instrument devices.
- Heat Trace installation for all outside interconnect Process, Water and Air piping.
- Temporary power throughout the facility.
- Installation of seven DCS cabinets with a fiber network interconnecting to a new control room and an existing control room approximately 3 miles away.
- Over 15 miles of Instrument cables pulled, tested, and terminated.
- Instrument air tubing to 87 air actuated valves.
- Loop Checks for up to 250 devices.
- Commissioning and Start-Up for 33 Systems
The scope also included a design-build for many systems throughout the three buildings, and Critical Project controls regarding P6 scheduling, lookaheads, productivity tracking and weekly budget reporting.